| MINISTER OF STATE (INDEPENDENT CHARGE) FOR ENVIRONMENT, FORESTS AND CLIMATE CHANGE (SHRI PRAKASH JAVADEKAR)
(a) The procurement of works contract for remediation work at Noor Mohammad Kunta Lake hazardous waste site in Telangana, and Closure and Containment of Dhapa Municipal Solid Waste site in West Bengal has been listed for rebidding. Closure and Containment of Kadapa Municipal Solid Waste site in Andhra Pradesh has been awarded. Remediation Action Plan for Hooghly hazardous waste site in West Bengal has been approved by Technical Expert Panel of the Ministry.
(b) The details of funds released and utilized under the CBIPMP are as under:
Sl. No. Implementing Agency Fund Released Fund Utilized
(Rs. in crore) (Rs. in crore)
1. Andhra Pradesh Pollution 26.16 18.95
Control Board
2. West Bengal Pollution 18.53 18.65
Control Board
3. Ministry of Environment 6.10 6.10
Forests and Climate Change
(c) The Project Oversight Committee has been constituted under the project and one meeting of the committee has been held on 13.09.2012.
(d) Under the CBIPM Project, National Programme for Rehabilitation of Polluted Sites (NPRPS) is being envisaged as Policy framework encompassing legal, institutional and financial components for remediation of hazardous waste site. The NPRPS is under finalisation. |